Rock Rapids has secured more than $1.4 million in Community Development Block Grant funding to support flood recovery buyouts involving 17 properties, including three that were not approved for FEMA assistance.
Grant Funding Supports 17 Buyouts
Two executed agreements with the Iowa Economic Development Authority provide a combined $1,422,065 through the Community Development Block Grant Disaster Recovery program.
According to the city, a $929,330 agreement covers its required 15% share of acquisition costs for 14 properties approved through FEMA’s buyout program. A separate $492,735 agreement supports acquisition and demolition for three properties FEMA denied.
Rock Rapids Chief Operating Officer Micah Freese says the funding arrangement for the 14 FEMA-approved properties originally called for FEMA to cover 75%, the state 10%, and the city the remaining 15%.
“So we applied for a community development block grant. And we were awarded that so that full 15% is being covered,” Freese said.
For the three properties FEMA denied, the city applied for CDBG funding to cover 100% of acquisition and demolition costs.
The funding comes as the city continues preparing contracts and other requirements for the 14-property FEMA project.
Council Revisits Bid Decisions
During a November 3rd special meeting, the city council revisited earlier bid decisions after Iowa Homeland Security requested additional documentation supporting the selection of higher-priced proposals.
Freese says the review involved using scoring matrices to evaluate the bids and document the council’s decisions.
“We went back through that process, rescinded the resolutions and reviewed the bids and went through scoring matrixes and then introduced new resolutions,” Freese said.
Contract Reviews and Asbestos Testing
At the time of the interview, contracts for legal services, asbestos testing, and demolition remained under review. Freese says the city’s legal team must finish reviewing the agreements before Iowa Homeland Security checks them for required federal provisions.
Once those reviews are complete and contracts are signed, work can move forward on closing documents and asbestos testing.
Freese says testing will help determine which homes can proceed toward demolition and which may require asbestos removal by a separate contractor first.
“So as for timing, we won’t know exactly until we get the reports back on asbestos,” Freese said.
Homes without asbestos could move through the process sooner, while properties requiring removal work would take additional time.
Demolition Timeline Varies by Property
Homeowners’ circumstances will also affect the schedule.
“Homeowners have different needs. Some are ready to close, some aren’t ready to close. You know, they might want to try to find a secondary house or whatever that is in the meantime. So, having a schedule per property isn’t feasible at this point,” Freese said.
For the FEMA-approved properties, Freese says the demolition contractor will have 90 days after each property closes to remove the home and meet the program’s requirements. That timeline applies to each property individually.
After demolition, Freese says the FEMA buyout properties will become green space, removing homes from areas vulnerable to future flooding.